The committee on Environmental Protection and energy will now come to order today, we have 1, agenda item before. The committee is subject, matter hearing regarding the Illinois, Commerce commission's, ruling on people's gas System modernization Program. Uh, we're going to begin with the roll, call to establish quorum to begin. Uh chairwoman Haden is present. Uh, Vice chair Ken. Alder laspada. Hey. Alder Ramirez. Alder Lopez. Thank you. Uh, Alder Tavares. Alderic. Joe Lopez. All your Crews. Alto Rodriguez, Sanchez. Alder, Conway, Alder, Reilly Alder Lawson. Alder clay. Alder, Martin Alderman, a hoppenworth All right. They're being 9 members present. We have a quorum. All right, joining us virtually, we have Alders Lawson. Oh excuse me. Sorry canson surprise. Uh and Yeah. And and Alderman Moore. And anybody else? All right, cool. Pearl. 59 could have a motion to approve, Alders, canoes and more as remote participation. All right. Aldo Rodriguez Sanchez so moves all those in favor. Say I all those opposed say nay and the opinion of the chairs, have it and Alders, canoes and more will be marked as present for today's meeting. Um, can you guys verify? You're there? Alder kutson. President. Thanks chair. Thank you Alderman, Moore. I'm here, I'm not on committee, but I just want to attend hear the information. It's fantastic. Thank you for being here. All right, I don't think we have any other non-members present at this time, we would begin public comment. Um, but none of you guys wanted to talk What's happening even today? All right, there being no public commenters that have signed up in a timely manner. The public comment period has concluded. Um, I would like to note that the committee did receive 1 written, public comment, and it's been sent out to you all via email. Our first order of business, is the rule 45 report from April, which was sent out to the committee. Could I have a motion to approve, the rule, 45 report, All right Alderman, now hoppenworth so moves all those in favor. Say I all those opposed say, nay the opinion of the chair of the eyes have it. Our only agenda item before the committee today is a subject matter. Hearing on the Illinois. Commerce commission's ruling on the people's gas System modernization project which is now being referred to as the pipe replacement project or PRP. on February 20th, the Illinois Commerce Commission issued a a ruling on people's gas, SMP after having positive for than a year. As part of people's gas rate hike case the ICC issued a ruling in November 2023, that paused the program and disallowed the entire proposed 2024, pipe replacement program. The pause allowed the ICC to investigate and evaluate, uh, the program which had come under increased scrutiny. After concerns about mismanagement surface and cost ballooned. the city which was a party to the rate increased case and the system modernization program evaluation as the ICC to reevaluate the pipe replacement project and to disallow pipe replacement. Projects that people's gas was not able to sufficiently justify in its February order, the ICC permitted people's gas to resume work within a limited scope and set of replacing its entire Natural Gas Pipe system. The ICC ruled that people's gas is only to retire at risk, gas pipes that present an acute safety risk by 2035, To ensure compliance with the order. The ICC will also appoint, a safety monitor, until the project is complete helping to create additional oversight and accountability. People's guests will also be required to provide a greater data on emissions to the city which will help realize our climate action plan. Climate change is real and it's already creating catastrophic disasters around the world. And here at home, From raging wildfires to record-breaking hurricanes the harsh realities that a warming Planet brings with the devastating consequences. This ruling takes that into consideration by disallowing people's gas to combine at risk. Pipe replacement with a broad broader system conversion as it had previously been doing. It's incumbent upon this body other lawmakers and Regulators to weigh the consequences of investing in systems of centuries, past that contribute to the destruction of our planet. The ruling strikes, the balance of acknowledging, the reality of needing to retire at risk pipes, while also making room for cleaner, innovative solutions in the future. Currently, the ICC is conducting a future of gas proceeding, which will develop an action plan for Illinois, Gas, Utilities future infrastructure Investments. In July, the IC will launch a pilot program that will use the existing natural gas infrastructure. We're here today to engage in a robust discussion about the ICC ruling, what it means for the city of Chicago, labor and rate payers, moving forward. And with that, I'd like to introduce our guests who will be providing testimony and have made themselves available for questions and answers today. Um we've aimed to keep a balanced panel with representative from people's gas labor. Unions environmental Advocates and environmental Advocates and consumer Advocates, all present to discuss the ruling. Um, before I do the intro, I'll recognize alderwoman Taylor, um, as being present, um, as a non-member, thank you for being here. so, Here. Oh, hey me, Mr. Blakemore There you go. Sorry. Uh, would you like to give public comment? All right, you guys, we're going to allow Mr. Blakemore to give public comment since he was here. Can we get 3 minutes on the clock? Okay, thank. Thank you very much. Uh, I see that this meeting is about Environmental Protection and energy now. Uh, maybe it's what I want to speak on is not specific dealing with uh, the gas system. However The big issue now. Is these are all uh, buildings on the sale. and uh, This committee has uh a responsibility to to make sure they are safe. and when I heard on the radio that, uh, uh, uh, the ventilation Now, wait a minute. Now, Mr. Blakemore, you not talking about people's gas. I'm talking about the pollution. How are you going to change these buildings over? And I heard that you don't even have to read says that the city will have to change the ventilation and that's a toxic environment. So it's gonna it's gonna be very difficult. But you all uh uh to make these empty uh uh buildings live above. because but you, you gonna have to change your ventilation and that's why should you and I'm gonna watch this Saga unfold. I know we're talking about the gas. However, I'm connecting the dots when I heard that that those buildings, you would have to change your envir, uh, your ventilation laws. Why would you do that? Because it's gonna come up too. Why? Because you put these people at risk, it is a health hazard and you're doing it for money. Where these empty building on let's say, or whoever owns them will be occupied. You're not thinking about the the environment in Impact that it would help on the citizen that will uh, live in the building. The elevator. I know people who deals with you, it's almost impossible But you to convert these buildings into uh, housing Without you changing ventilation. so, that's why it's very, very important of for me to come up And to speak up. They say the city gonna have to change their ventilation and I'm a watch. This struggle un unfold. I'mma watch it unfold and it you. It's impossible. Why would you load your standards? Why would you even consider changing the ventilation laws in this city? so, come Thank you, Mr. Blakemore All right to our guests. Um thank you for joining us today. Um so with us today for the committee, we have Maria boccanera. The new president of people's gas if you guys want to give a nod or a symbol because I know you're not exactly in the order that I'm going to introduce you. All right. We've got, uh, Sean garrage with Local 18, 007, we've got Mark pulos with local 150. We've got Abraham scar, our state director and energy, uh, in utilities program director from the Illinois, public, interest research group, We've got Sarah moscowitz, our executive director of citizens Utility Board. Jared picho, I always mess with your name Jared. I'm so sorry Jared Politico. Uh, Deputy Commissioner of the Department of environment and Jay kale, our Deputy Commissioner for the Department of Transportation, uh, so Jared and Jay aren't presenting today, but as representatives from relevant City departments, they're here to answer questions. Maybe during the Q&A period, that might come up from committee members. um, With that. I'm just going to turn it over to uh president bokra from people's gas. Good morning. Can you hear me okay? Yes, good. Okay, good morning, chair Haden members of the committee and fellow stakeholders. My name is Maria Bo kgr for the record that is spelled m, a r. I a b o c. A n e g, r a and I'm proud to serve as the president of people's gas which provides natural gas service to over 870,000 homes and businesses across our city. joining me today are several members of my team in the event that there are, um, technical or other questions that may need assistance in being asked, thank you for the opportunity to appear today at people's gas. We are committed to the future of Chicago. Its safety resilience and environmental progress. I am born and raised in Illinois and I am the proud daughter of an immigrant father and a mother who was a migrant Farm worker. As the first in my family to attend college. I'm an attorney by training and I have spent most of my career in public service, including appointments from Governor's Quinn and rounder to the Illinois, workers compensation commission as an arbitrator and most recently, by Governor by Governor pritzker, as a commissioner to the Illinois, Commerce Commission where I oversaw, uh, utility regulation. I very much bring those values of service integrity and kandare into the role that I have today. As you know, Chicago's natural gas system is 1 of the oldest in the country, some pipe State, back to the 1800s. these aging pipes, pose safety, risks and release methane a potent greenhouse gas. That's why people's gas has embarked on 1 of the nation's largest infrastructure. Modernization efforts, replacing outdated cast iron and bare steel pipes with modern materials, Since 2011, We have replaced over 1,400 miles of pipe about 38% of our goal. Resulting in fewer leaks, significant carbon reductions and increased efficiency. This work is fundamentally about 2 things. Safety and reliability. We along with our labor Partners, whom you will hear from later today. Work every day to ensure the safety and reliability of our system and has done. So for over 175 years Our system supports the heat, hot water, and Industrial activity that sustains, Chicago's residents and its vibrant economy. People's gas is regulated by the Illinois, Commerce Commission, or the ICC. The ICC ordered an independent engineering study, and found that more than 80% of the iron pipes in our Energy Delivery system are at the end of their useful life. The study determined that these pipes have less than 15 years of life left today. That number is less than 10 years. In 2023, the ICC, paused our pipe replacement program for a comprehensive review. We disagreed with the pause believing alongside independent Engineers that the most at risk. Type needed urgent replacement. The icc's new February, 2025 order allows us to restart, That work, directing us to replace approximately 1100 miles of diameter pipe, 36 inch or less by 2035, a safety monitor will now oversee, this work. We applaud and welcome the icc's clarity and clear directives. So, what is next? In response to the icc's new direction, we have re-examined our approach to replacing risky pipe under this new pipe replacement program or PRP approximately 1100 miles of older pipe 36 in, in diameter or smaller will be need to be replaced by 2035. Restarting. This program is no small task. We are rebuilding more rebuilding momentum after a 2-year slowdown, rehiring workers coordinating with the city and nearly 30 underground, utility stakeholders and preparing for a significant ramp up. Performing this volume of construction. Under the accelerated, new timeline will require constant close, collaboration, and coordinating. We have already had several productive discussions with C Dot and with the city's water department on how we can further collaborate, including incorporating, some of the Lessons Learned of the past to allow both us and the city to be more productive efficient and least disruptive. Achieving the 2035 and Target will require us now to prioritize speed Above All Else. We will need to significantly ramped up the miles of pipe. We replaced each year each year and we may need to rethink some other aspects of the program that deliver safety and reliability benefits. Internally. We are currently looking at both a short-term immediate plan which focuses on 2025 and 2026 and our longer term plan from 2027 and years Beyond. We continue to evaluate all aspects of excuse me, all aspects, and impacts of the icc's order on our ability to meet the accelerated timeline, including the longer term impact on our operations and our Capital planning. For the remainder of this year, a lot of our near-term work will focus on resuming, pause projects, or pre-approved projects that have already gone through the OUC project Pro process. But I have to say that modernizing our system isn't just about safety. It's really about also preparing for a low carbon future. Since joining, the epa's methane ChalleNGe Program in 2017, we have avoided over 1500 tons of methane emissions. The equivalent of 107 million, miles driven by gas, powered passenger vehicles. We are also investing in Innovation at our training facility in Little Village. We recently, completed successful testing of hydrogen blending which emits no carbon when carbon when burned hydrogen will be a key. Part of Illinois's clean energy economy, and we are preparing our infrastructure for that future. And in partnership with green era, we have begun, delivering renewable natural gas or RNG from a Southside facility. That was once a Brownfield. Uh, that now transformed food waste into clean energy enough to heat, 2100 homes annually, and the potential to double So in closing, I want to reaffirm our values, safety reliability, sustainability, and partnership. We believe decarbonization and energy, reliability are not competing priorities. They must go hand in hand at people's gas. We are committed to thoughtful people, centered progress. And so I think you and I welcome your questions and comments at the conclusion of the hearing, thank you for your time. Thank you very much Maria. All right, um, we are moving on to Shang garage from 18 007. Chair Haden, distinguished members of the city council. Good morning. My name is Sean Gorge. I'm the business manager of utility Workers, Union of America, gas Workers, Local 18, 007, A representative 1,000 hourly employees of people's gas. Who are responsible for safely, delivering natural gas and Staffing. The customer care center. Our membership is almost 80% diverse. 30% of which are veterans more than half live in the city of Chicago and are also customers of people's gas and 95% live in the Chicagoland area. We reflected the diversity of pgl's, customer base and we are on the job 24/7. And every 1 of the 234 square miles of City Chicago. I have been a crew leader in the distribution Department with more than 30 years of experience. Throughout my career, I have seen firsthand the poor condition of our underground pipes. I can confirm for you that what the engineering experts have said for years about the underground pipe reaching the end of its useful life. That is absolutely true. Many of the pipes are 100 years old. Reaching. I'm sorry, 100 years old for over a decade people's gas. Through the work of my membership have been replacing that pipe and an accelerated pace. However, as you know, that work was paused by the ICC for the past year. I'm here to talk to you about the impact of that pause. Working in the national natural gas industry. The first thing you learn about a safety Natural gas is a safe clean environmentally friendly low-cost energy source. When it's controlled. however, when the system that it's delivering, the product is compromised old, and nearing the end of its useful life, gases dangerous, It is dangerous for my members to have to work on the pipe that is leaking decaying and crumbling. It is dangerous for our customers when leaks occur underground and migrate to their infrastructure. the pause in the company's accelerated pipe replacement program caused my members to have to work on more leaking pipe because the program lost the year, It is actually more than a year because people's gas is still not restarted, the accelerated program and even when they do will take more than a year to get production back up to the PACE, it was working under. This will cause my members to have to work on dangerous leaks. They otherwise would not have had to because they're leaking. Pipe would have been replaced. Customers will be exposed to the dangers of more leaks as well. Let's pray. We don't have an explosion that could have been prevented. My member safety is of the utmost importance to me, but equally important is the safety of our customers. There are several other impacts as well. Let me list them for you. With the pause, the company has drastically reduced. The number of gas worker Union hires because there's less work. They have also had to pull back an internal promotion for seasonal, employees, moving into regular positions. Remember when I opened that 80% of my membership is diverse. 30% of our veterans and the majority live in the city of Chicago. Having less jobs. No, careers is not good for the local economy. The accelerator program required, many more hours of work from my members. It was grueling physically demanding work, but my members were happy to do it. We had a mission replaced bad pipe and protect our fellow members and the residents of the city of Chicago. The reward for it was additional pay for the overtime required. The pause drastically reduced earning potential for my membership. Some members close to retirement chose to retire. due to learning to the lower earning potential causing a loss of experience, Morale. The pause also caused a drop in morale for people's gas Workforce. Suddenly, suddenly the project that members had put their Blood Sweat and Tears into a stopped, We Believe without a valid reason. Why would somebody want to? Why would somebody want to leave leaking pipe in the ground longer? Our mission was abandoned hours were reduced paychecks were drastically reduced. Members viewed the pause as an attack on our industry. Our livelihoods are careers. It's not easy to be a gas utility employee. Long hours, physical demands working in all kinds of heat, cold rain snow exposed to traffic hazards crime, in the city. The hazards of working with natural gas being called out of bed to address emergencies and the impacts that our family lives. Gas isn't going anywhere. It is going to be needed for decades or more. arguments made for minimizing investment in the system, whether pipes or people Because of electric electrification are not realistic. electrification is decades away, even if it happens to any sort of significant sale scale, However, replacing the pipes cannot wait. Shifting entirely to electricity result in skyrocketing energy costs for the city's most vulnerable residents. Natural gas is more affordable and reliable option for heating for Chicago's fluctuating climate. Thank you for the opportunity to express the views of my 1000 member long, long strong logo. Thank you very much. Um before we move on to Mark just a reminder to remember's we're not actually here in a hearing about building electrification. Um and I appreciate the the appreciate the the testimony, but we are talking about the case and the impact on people's gas and consumers, and various stakeholders. Um, uh, so now we're going to hear from Mark pulos from local 150 Good afternoon, Madam chairwoman members of the committee. My name is Mark pus executive director of the Indiana, Illinois, and Iowa foundation. For fair Contracting, the Labor Management Group of the operating engineers. Local 150 representing nearly 23,000 hard-working men and women throughout the city of Chicago and Northern Illinois. I come before you today to voice our full support for the icc's. February decision to lift the pause on the people's gas pipe replacement program and to encourage continued to investment in this critical infrastructure program, the decision to reinstate and refocus the pipeline replacement. Work makes a critical step forward for infrastructure, safety. Jobs the creation of long-term economic interests for its Chicago residents. Let me begin. By talking about jobs. the reinstatement of the program creates substantial employment opportunities for members of the international Union of operating engineers, local 150 and numerous other Building Trades organiza organizations across Chicago with renewed focus and accelerated timeline. This infrastructure program were more than double the annual pipeline replacement rate from a proximately 50 m to 110 m per year, This acceleration, translate directly into thousands of good paying family, supporting union jobs, the pipeline replacement work requires specialized, heavy equipment operators, welders laborers and many other skilled trades. Representing a significant long-term employment opportunity for our Workforce for local 150 specifically. This program provides consistent stable employment for our members who operate heavy machinery essential for excavation pipe installation and site restoration throughout the Project's. Duration, local 150 members are trained at our hundred million dollar facility. in Wilmington Illinois where they received specialized instruction in Gas Distribution, safety excavation and utility coordination. That training combined with union experience leads to higher productivity fewer, safety incidents and greater project success. Moreover, this program is governed by a project, labor agreement, ensuring it, it is completed by locally trained. Union trades, people at prevailing wages and benefits that not only promotes quality and efficiency, but guarantees that this investment circulates back into the local economy supporting Working Families and small businesses throughout the city of Chicago. Beyond direct employment. The PRP program creates significant economic multiplier effects throughout Chicago's economy material, suppliers equipment, manufacturers, Transportation companies, and local businesses all benefit from The increased economic activity. Generated by this infrastructure program, every dollar spent on infrastructure Improvement, generates additional economic value through these Supply chains and increase consumer spending by employing workers, As for the safety and reliability, the primary purpose of the PRP is addressing critical public. Safety, concerns. Chicago's aging gas distribution system includes pipes that have been in service since the 19th century. Well beyond their intended lifespan, these outdated cast iron and ductile iron pipes are prone to the leaks which both significant safety risks to neighborhoods throughout the city. The CC investigation confirmed that these aging pipes represent a genuine safety hazard and must be addressed. The February decision refocuses efforts specifically on the highest risk infrastructure components, ensuring that safety priorities derive, the program, rather than broader modernization goals, the establishment of a 2035 deadline. Aligns with the recommendation from the engineering as experts and federal safety directive from the US pipeline hazards material, safety administration. In terms of consumer costs, the ICC balanced decision. The the icc's balanced decision to reflects careful consideration of both safety requirements and consumer, affordability concerns by refocusing the program specifically on high-risk pipes and the icc's decision, reduces the scope and cost of the program. The revised approach eliminated, the replacement of 49. M of large cast iron pipe with longer remaining useful life. Saving approximately 330 million in terms of the economy from a broader economic perspective investing in modernized infrastructure. Now, yields substantial long-term benefits. Modern pipeline systems are more energy, efficient and significantly reduce methane leakage. Which represents both environmental harm and wasted resources that customers ultimately pay for the improved system. Will require less ongoing maintenance reducing long-term operational costs that would otherwise be passed on to customers. The icc's decision to reinstate and refocus the program represents a carefully balanced approach that prioritizes Public, Safety creates good paying union jobs and implements responsible controls to protect consumers. The decision serves the best interest of Chicago's workers residents and long-term. Infrastructure needs, Local 150 and FFC commends. The icc's decision to lift the ban and urges this committee to support the icc's decision and work collaboratively, with labor organizations, utility providers and Regulators to ensure the successful implementation of this critical infrastructure program. I thank you for your time and available for questions. Thank you Mark. Um, before we move on I just want to recognize uh alter 6 to Lopez and Riley for purposes of Quorum. Thank you for attending. All right, um we're now going to hear from apesar with the Illinois public interest research group. Good morning. Uh chairperson had and vice chairperson kuden, honorable members of the committee, thank you for the opportunity to testify today. Uh, my name is Abe scar, I'm the director of Illinois per. And for over 8 years, we've watched dog people's gas and its troubled pipe retirement program. Uh, we were an active party in the ICC investigation. That's the subject of today's hearing. I'd like to thank, uh, chair Haden, and committee staff, for organizing today's hearing and engaging Council more proactively with people's gas, this proactive and ongoing engagement will be critical to address the challenges, facing our city and gas utility, as we transition to safer cleaner energy to heat our homes. I also want to thank and welcome Miss spoken egg as people's gas new president. Uh I appreciate her comments about working with stakeholders and interest in innovation. Thanks to the ICC investigation and its mandate for reform, the people's gas pipe retirement program is at an inflection point. This is an important opportunity to build a better program for the people of Chicago. Uh, I remain highly critical of how the program has been run to date. I want to focus my testimony on what I see as 2 opportunity to positively transform this program. Going forward, uh, first a better focus on mitigating safety risks via a new approach to risk ranking and second using many more tools, Beyond full pipe replacement uh, to cost-effectively mitigate risk. So first, a better focus on mitigating safety risks. This is important for 2 primary reasons, Effectiveness and cost Effectiveness. That is achieving the greatest possible reduction in safety risk and doing so, for the least amount of money, which means less severe rate hikes for Chicagoans. For all of its safety rhetoric. Like what you've heard today? People's gas has failed to properly. Prioritize safety, in its pipe, retirement efforts to date, both a 2015 audit and the 2020 engineering study, which has been referenced multiple times today. Found that indicators of risk were not declining in any proportion to the billions of dollars people's gas was spending on pipe retirement. and in the investigation, uh, perg experts, demonstrated with unrebutted testimony, that people's gas method for measuring risk and risk ranking neighborhoods for retirement is fundamentally broken. Not only uh, were the methods not probabilistic, that's the industry, best practice. Uh, the methods suffered from Fatal flaws that rendered its risk rankings inaccurate Again and to be clear people's guys had multiple opportunities in the investigation to rebut these conclusions by our experts. It did not Uh so now people's guess is contracted with a janitor Corporation to develop a new risk ranking methodology and this methodology is purportedly, probabilistic again, a industry. Best practice, this is good. We applaud that. uh however we still have reason to worry that the methodology that people's gas is developing will not perform as well as it could or should uh during the investigation people's gas and Jana refused to share details, such that our experts could verify the veracity of the new methodology. Um, and I don't think it's uh uh uh, uh, people's gases, embracing transparency. Now, uh, 1 of the, uh, things that the final order did was encourage people's gas to hold risk, ranking workshops with stakeholders and so far as it has scheduled a single 1 hour Workshop, which we believe is insufficient, Uh, but again, this is an opportunity to adopt a rigorous transparent risk methodology doing. So would better achieve the safety outcomes. We all want minimize rate hikes and critically help rebuild public trust in a program. That's been dogged by years of mismanagement and cost overruns. I sincerely hope that utility management will seize the opportunity to get better results and become more collaborative partner with the city and other stakeholders. Um so the second opportunity is to use many more tools to cost effectively mitigate safety risks. Um, notably the ICC order did not order people's gas to replace all of its at risk. Iron pipes by 2035 instead it ordered it to retire them. I think that's really critical. We've heard a lot today about how the order is to replace all the pipes by 2035 that's not the order. Its retirement Um, this distinction is important. As it does not presuppose a single strategy replacement, uh, that is replacing old pipes with new pipes made of modern material. And instead leaves open multiple strategies, uh, such as advanced repair pipe relining and other non-profits. These strategies have many uh, potential benefits, including the potential to be much less expensive. Uh, and as such these strategies could achieve desired safety outcomes, while costing less and facilitating rather than frustrating, the transition to clean energy homes. Um, to take just 1 example of these Alternatives, uh, cured in place lining, uh, has been used successfully in parts of the United States, Europe and Japan for more than 30 years. Uh, there's 1 commercial. and in fact, in 2013, uh, people's gas used Star Line, excuse me, I think that's 2023. Have my notes wrong, uh, people's guys, use Starline cured in place lining on a 200, uh, foot 24 inch cast iron pipe initially installed in 1909. Uh, that's a main feeder of gas for downtown. So this technology is not going to be appropriate to retire all of the remaining at risk pipe and the people's gas system, but it along with other alternatives to full on replacement must be considered. Uh, the ICC investigation also created a workshop process to consider such non-profits uh embracing a suite of retirement options, rather than defaulting to a replacement. Uh, is the second opportunity that people's guess has, to use this inflection point, to positively transform, its pipe, retirement efforts, Uh again, thank you to the committee for the opportunity to speak today and I welcome your questions and look forward to the discussion. Thank you, Abe. We will lastly hear from Sarah moscowitz of the citizens Utility Board. Good morning, everybody. Excuse me. Allergies. Um, thank you, chair Haden. Thank you to committee staff and thanks, you all for the opportunity to testify here today. I appreciate the committee for conducting this hearing at a critical moment in the discourse over our cities gas system. I was invited here today to talk mostly about the affordability impacts for people's gas, customers of their past. Um practices with pipe replacement, I'm not going to repeat what others have said. I agree with all of a lot of it, not all of it. Um, but I do want to just highlight that those who have said, who have congratulated the ICC on its recent order. Um, refocusing the program and allowing us to move forward in a more prudent way. I think this is overall a good thing and as Abe pointed out, we have some opportunities, but there is still great need to be And we are looking, we we're hopeful that there will be a will be a more collaborative process going forward that takes into account. Um, the the Prudence of Investments and the kinds of impacts on rate, payers of um, unchecked spending on the utilities part. So only a few weeks ago, people's gas announced the largest profits in its history. 224 million earned last year. I'm here to remind everybody that while the utility is breaking records for Prosperity, the story of its more than 800,000 customers here in Chicago, sounds a bit like a broken record too. As the winter season wraps up people's gas, customers are still struggling in a heating affordability crisis that you've already heard about from me. It's a problem that unfortunately shows no sign of abating. With gas commodity prices jumping back up and the Spectre of yet another people's gas rate. Hike looming. We don't know when that's coming but we're pretty sure it's coming. and now apparently it seems that Federal Li Heap program is on The Chopping Block outside of this jurisdiction, but also on my mind very much according to the utilities most recent collections filing with the commission, nearly 1 in 5 of its customers was more than 30 days behind on payments to the company as of the end of March. And more than 1 in 4, customers had incurred late fees on their heating bills. All told people's gas customers were a collective, 94 million dollars in debt to the utility. The cost of staying warm in the winter is forcing, large parts of the city to the financial Brink and as widespread as a suffering has been, it has been most glaring in Chicago's black and brown neighborhoods where as many as half of all people's gas customers faced chronic debts. The utility has to submit zip code, level data on its collection activities, each month, I encourage, um, members of the city council to look up their local zip codes. It's uh, Shocking. Last January, people's ushered in the largest rate, hike for a gas utility in Illinois, history at the time, the company reassured. Everybody that it's increased gas delivery charges would be offset by lower costs for the gas itself on the commodity Market. Unfortunately, a guest wrong. Gas prices are rising again, which means people's gas. Customers are getting squeezed now on both ends of their heating bills paying more for people's to both acquire and deliver fuel to their homes. As a Tribune recently reported the gas prices that people's customers paid last month. Where the second highest that the utility has charged during any April. In the last decade last month, the price per therm was 52.79 cents this month in May it's 59 cents per therm even higher Meanwhile the utilities record-breaking profit in 2024 represents the 6-time in 7 years. It is shattered, its own high water, mark for earnings. the utility is entitled to collect a profit as we all know, from its customers for the money, it spends replacing pipes, which creates an incentive for it to rip up everything Before the icc's decisions. At the end of 2023, people's gas for more than a decade had, been replacing gas Mains without any judicious analysis of the need and then enjoying massive profits as a result. Fortunately, as mentioned earlier today, State Regulators at the ICC have put a stop to the utilities indiscriminate approach to pipe replacement ruled this year to play some checks on people spending more hopeful like I said that this new level of accountability. Well, at least slow the pace at which heating bills increase for people's customers. Pi pipe replacement work. I'll note isn't the only reason the Earth is Shifting under the feet of energy consumers. Right now, our city and state both have said, ambitious, clean energy, and carbon reduction goals. And as more customers explore and make the jump to electric heat, it leaves a dwindling. Number of people's customers to Bear the ongoing costs of replacing gas pipes. We need to devise a plan to avoid the gas death. Spiral whereby the Hefty costs of maintaining. The city's Legacy. Gas pipes is foisted dist, disproportionately on lower income, customers who are left to stranded on the system, Last year, the Illinois Commerce Commission, began a process. A future of gas investigation, to explore ways to navigate this Challenge, and plans to publish findings from this review next year. The review is not happening in secret, quite the contrary. It's taking the form of a series of public workshops and working groups with multiple opportunities for parties to weigh in in real time and Via written comment. Actually, I believe uh, just about everybody on this morning's panel. Uh, plus many other stakeholders are involved in the future of gas process. And uh, doing what they can to shape its outputs. We'll see how that goes. I think a lot of us involved in utility policy at both. The state and city level will be closely watching in the meantime. However, Chicagoans will have to muddle through more winters of high gas bills to pay for a fossil fuel system, that bucks the city's climate goals. Um, so there are a lot of good reasons for this committee to continue, keeping an eye, on the utilities activities and I look forward to us working together. Moving forward. Thank you, Sarah. Um, before we open up for uh questions. Um, I will say that um you know, we've had I think multiple engagements with all parties uh who have joined us today um throughout uh the last year during the freeze. Um and I anticipate through our committee will have multiple engagements, um, with this group going forward through the future of gas. But also want to mention that um uh president booner and her team. Um have uh, are in talks with us as well about uh figuring out a regular yearly kind of hearing um uh the way we bring ComEd um, before for summer preparedness so we're So we're in some talks of shaking out the details, um, outside of rate case and things of that sort, uh, sorts, uh, to talk about even maybe like winter preparedness. And, um, so we look forward to working with your team. Um, President bokeh on figuring out a more regular Cadence for people's gas to come. And be able to uh share what they're doing and working on before Council. All right. Um, on stack I've got uh, Alder Martin and then Alder Conway. Thanks very much chair. Um, good morning everybody. Um, Most of my questions I think are best for people's uh, but if anyone else needs to chime in, uh let me know. Uh, first more of a request through the chair is people's able to send us a map or some other information that specifies where the uh 1100 miles of piping to replace Rhett retires located. Yeah, Alderman, thank you for the question. And we are able to uh, provide you with a visual map where you can see um, uh, where that plastic pipe lays, uh, where that cidi pipe lives, and you can have that, um, on a map. We're happy to get that to you terrific. Um, and then kind of from a timing perspective. I think I heard you Sharon your remarks that for the next several years, maybe leading up to 2027 that you're looking to ramp up and then you're going to be in a different phase of replacement uh starting around 2027 um in terms of the oversight and accountability that we're going to be providing as a body in the coming years point in time. Are you expecting that you will essentially hit your Peak capacity in terms of replacement in approximately approximately 2027 and then stay steady? Uh, in terms of the average number Of miles that are replaced annually, right? Um, well, so you are correct Alderman. That uh, there's really 2 sort of phases that we're looking at this, um, from from that angle. Um, and this is really sort of a, the engineering approach, if you will that we are still evaluating, um, the the low-hanging fruit, as we're calling like, it's the ramp up period that 2025 through 2026. Um, that is based around idea that we have designs, um, and things that were approved, like I mentioned ready to go. Those are things that we could do today. Um, as we continue to evaluate, you know, what does this order say, uh, we should be prioritizing. Obviously, it's very clear that it's the CI 36 inch or less by a date certain. That's very clear there's other components within that 200 Page Plus order, um, that we still need to evaluate from an engineering perspective. Is what can we do? What should we do? And Is it feasible, um, from an engineering perspective and then there's just the actual figuring out what are the external constraints that may limit or inhibit that run rate that you're asking about. And so I can't give you, um, the exact mileage that we anticipate. And then, of course, you know, as um, as our stakeholders here have pointed out, you know, all of this still is subject to regulatory scrutiny, uh, understandably. So, um, and so to the extent that, uh, this will be scrutinized by the safety monitor, um, or, you know, the ICC that will largely helped, uh, dictate. You know what? That run rate looks like like 2027 and Beyond but that is the anticipated sort of longer term approach starting in 2027 understood, that's helpful. When it comes to, some of the external factors that you mentioned, I was wondering how you are wrapping your heads around the tariffs that have been imposed that have been threatened and how that could impact, um, uh, the cost of this ongoing work. Yeah, that that's a great question. Uh, let me start by saying that, um, you know, like many other Industries we are not immune to, um, you know, Global pressures from from these types of tariffs. Uh, what I can say is number 1. We do not anticipate any tariff impacts to our safety and reliability which is Paramount above everything else. Uh second what I will also also add is that we are evaluating what the Tariff impacts are to our particular business. As it relates to people's gas, um, 2 things on that front. Um, we are fortunate enough that most of our natural gas is sourced domestically. Uh, so we are not seeing a tariff impact on that front. Simultaneously on the material side. Um, I have been in contact with our supply chain and procurement. Uh there is um that too most of our uh materials are also sourced domestically as it relates to pgl. Um and lastly, what I would say is we continue to monitor those things with safe um with our supply chain and our procurement offices, they are working with our legal teams in terms of what is that potential tariff impact due to existing vendor contracts? Um, supplier agreements Etc. And then the Last thing I would add Alderman is that we internally at pgl are asking ourselves. How do we embed any potential tariff impacts? Should they come and be able to recalibrate how we are planning and forecasting? Uh, any impacts on that spend noted? Are there understanding that? I think you mentioned most of the materials currently are sourced domestically, are there any materials that jump to mind that point in time are not sourced domestically? That's a great question. I don't, I don't have the exact details on what that might be but I could definitely take a a look and see, you know, where if there's anything coming that are not sourced domestically, that may be impacted, but right now, I don't have that. Okay. And I think through the chair, if you can, just note areas specific, um, types of materials that at least, you'll be focused on understanding that. Um, there could be a lot of play in the joints. I think it's important for us as many people are asking us what's the on the ground impacts of some of these proposed tariffs actual tariffs that we be able to speak to that? And I think that infrastructure work maybe isn't always something that comes to mind. Sure, for residents, but it would be good to know if there is potentially a tariff impact that we can uplift that. Absolutely. with regard to the, uh, 1100 miles of piping at a high level, when and understanding that, uh, What the ICC has directed there in terms of the next approximately, 10 years. Where, when would you be looking at a pipe as a candidate for lining as opposed to replacement? That's a great question. I appreciate that. I think that kind of, um, is a nice tie-in to, you know, some of, um, AES remarks about those npas. Um, you know, uh, 1 of the things that the icc's order did, uh, direct us to do, and we do intend on doing, is it is asking us to look at non-pipelined in the remarks by Perth? Um we are still in the process of developing, what that coordination, and those workshops could look like. Um, so I think that that would be the appropriate form to to talk about those things, um, in terms of which pipes, um, I'm not an engineer. I don't know if that is something that is feasibly, you know? We could we embed that in that Jana model that that Abe spoke of. Um, we are hosting, um, You know, that workshop and and possibly more, but I think that those are 2 forms that are coming to my mind where that would be the appropriate, uh, way to lay that out in in collaboration, with our stakeholders. um, My second to last question is actually around stakeholder engagement. I know that that's something where both in your remarks and in Mr. Scar's remarks. Um, there was an emphasis on breathing new life into that external, um, engagement stakeholders including but not limited to the community. Um, can you share a little bit more about what's planned or at least contemplated in the next year or so yeah, sure. I let me start by saying that, you know, I think you you heard in my remarks that, you know, most of my career has been in public service. And so I'm, I'm acutely aware of some of the, um, challenges that, uh, public servants, like, yourselves face in in sort of wanting to make sure that, uh, there is that stakeholder engagement, and that that same desire carries a lot into my role now. So, so number 1. I am committed to, uh, making sure that we are reevaluating the ways that we have been engaging in the ways that we want to engage going forward. I think that the icc's order, um, has ushered in that new opportunity that we've been talking about. Um, I've mentioned the workshops, I think, you know, Part of sort of my first 100 days, um, with the help of our regulatory teams, and my operations teams. Um, we really been hitting the ground running to sort of try to hit that reset button and getting out into um meeting with folks that perhaps we haven't met with in a long time. Um, so I think to answer your question it's it's both you know there's opportunities within the pipe replacement program itself but as an organization too um it still is a priority for us and so like chair hat and said, you know we we have met with her office and um I am Committed to, you know, talking to other offices as needed. But I think there's a lot of opportunity there. And I also want to commend um, whack Energy Group for sort of bringing in someone from the outside to take a fresh look at, you know, how have we been doing that? Stakeholder engagement, and how can we do that differently? And so, I hope that answers your question. Yeah, yeah. And I think some of it can be follow-up. Both through the chair as well as with our own offices, working with your government, relations team. Um, uh wanted to quickly commend you, for noting, uh, uh, the ongoing coordination and collaboration with green era. Uh, many of us have toured that facility in recent years, both current term and prior term. Um, I know that there was a ribbon cutting recently, the governor pritzker among others has had attended and it's a wonderful organization. I'm glad to uh, hear that uplifted in your remarks. My last question is for the city, um, I was wondering if you could speak at a high level at C do, um how you um in the department are working to incorporate? The icc's ruling when it comes to C. Dot's planned and recommended resurfacing including but not limited to our aldermanic menu program. We start, uh, meeting with the stakeholders people's gas water department and uh, Cedar's menu programs to see incorporate and see that, how does it affect? So we waiting for people's gases plants. So as in our coordination process through, you see we will coordinate those. Okay? I I would just encourage you and your colleagues, in advance of enduring, our annual menu meetings, um to uplift uh any of the critical um pipeline replacement work, that needs to happen. That was part of why it asked people's at the outset for that map. I think it's important for us to make it's important for us to make sure that we're working with you all to prioritize what's needed. And uh, that part of that, probably involves looking at, of course, boy, uh, dwm is doing with water main replacement, but also what people's is doing, um, with their pipeline replacement so that we're minimizing the frequency of opening up our roads. So thanks in advance for that. And thank you chair. Thank you. All right up next I've got Alder Conway, followed followed by Alder the spa, followed by Alderman Moore, followed by Alder, siko Lopez, and then, Alder Lopez. So uh, Alder Conway. Wonderful. Oh, did you have a quick question? oh, I I was doing by order of hands raised but I uh I think think Alderaan Moore is the only 1 not on the committee, I can, I can I can scooch you up ahead. Uh, if you got, the, the open Lopez, is so place to be, you're what? Alderman Conway. Uh, thank you. Um, And also certainly want to want to appreciate the testimony of all of you. Uh uh President boccanera. Uh, Mr. Pulos and Mr. George as well as Mr Scar and Miss Moscow. It's, I've always learned a lot in these hearings. I too am not an engineer, so, so always appreciate it. Uh, and I also do, uh, uh, misspoke in Agra want to thank you for replacing that pipe at 8th and Wabash, knowing it was 160 year old and, and on the edge of the 34th Ward. um, but and then the same breath, I do really want to commend the, the ICC for for taking a look at the at the regulatory structure here uh, based on um, You know, their lengthy report documenting the, uh, failure to prioritize high-risk pipe significant cost overruns. The crippling debt that that that many Chicagoans have to people's gas. Um so I I I really and I'm glad you're all happy with the report but when I read it it was 200. Whatever pages long and it actually didn't seem like it gave you all that specific of guidance here in that. So I'm glad you were able to sort of see guidance in there, but I thought it was a little difficult. my my first set of questions as as was largely asked by Alderman Martin. But, uh, I would note that the report indicated that in the in recent history, people's gas has only replaced about 49 miles per year of pipe and set in the future. The report said between 74 and 222 miles per year. Uh, you and your, um, spoken Agra you and your report said, uh, you anticipated 110 miles a year. Um, I know, Alderman, Martin, um, Uh asked some questions on this. But if there's anything else you want to say about the ability to, to, to pull that off and perhaps you can, if there's anything more to say about the possibility of reigning in that as well and the other options. That Mr. Scar said, I want to give you that opportunity. Yeah, thank. Thank you for the, uh, remarks. And, and for the question Alderman, um, I think what I would add is, um, you know, it's it's not lost on us that that perhaps might be the big elephant in the room is, is how how do you get it done. And, and um, you know, as I mentioned earlier, that's certainly something that we're looking at, um, when we think about feasibility, um, outside of the engineering component of that, um, I think that 1 of the larger constraints will be the ability to coordinate, um, with our partners at at COD, um, you know, that is a significant potential run rate, um, if, if that is the path, and if that is the, uh, run rate at which, um, we are allowed to go either through the safety through, um, through the icc's blessing, so to speak, um, that is now without um, significant challenges. Um, this is no doubt a very complex, um, type of construction project 1 of the larger ones in the United States. Uh we are in a very dense Urban environment. We have nearly 30 stakeholders, 30 different permits, we have to get through. Uh, we are looking at, um, uh, to to piggy back off a Deputy, Commissioner khalil's comments, you know, we have begun discussions with the city about, you know, how do we know, how do we think about gaining efficiencies together, whether it's, uh, reforming, uh, design duration design process? Whether it's looking at, can we reform? Uh, Permitting processes permitting duration. Um, does that come at a cost and if so, what is that cost? Those are all things that we're looking at. Um, and so I I don't have an answer to you for you today as to what what the magic miles is per year. It will largely depend on some of the things that we've started talking about. Um, and then I will just say, on on the NPA side. Like I said, you know, the plan is for us to um get stakeholders together and figure out together. Where would it make the most sense? Um, is there? Anything that the probabilistic model can help inform that process that planning process. Uh, where is at least disruptive to the citizens of Chicago? What does that cost relative to, um, an alternative like a CI replacement and so, all those things still need to get worked out. Um, Okay. It seems like it seems like a Herculean task, so I so I appreciate. And to the extent that the city can safely cut regulatory, red tape here while allowing us to can hope that's not what's going to hold. Uh hold it up. Um the the report was also pretty scathing about. Cost overruns in the past to, to quote something on page 185, it says pgl's inability produced 2 to produce a cost estimate is a problem of their own making indicative of people's gas, ongoing. Failure to cost effectively manage a multi-decade multi-billion dollar, infrastructure program, um, noting that we're trying to look forward and not backward, um, how does people's gas plan to effectively manage costs going forward in a, in a better way that then they have uh in the past. Yeah, I I appreciate the the remarks. Um it it certainly is not lost on us, you know, having having read that report as well. Um a couple things I'll say to that um to get to the point. Yes, we are definitely looking at, you know, what were our project controls um and what can we do differently? Um, whether it's better. Cost estimating, uh, Tools uh Lessons Learned. Um I think that we will also be um um looking to the safety monitor to make sure that um if there is any input uh from from that um, From that safety monitor, in terms of, are we meeting the metrics? What are the metrics? And at, what point do we recalibrate as necessary? Uh, just to give you an example, Alderman. You know, 1 of the things that we've done internally already is, you know, we've, uh, sort of done a SMP, uh, former, you know, project sort of dissection, you know. Let's take a look at how did, how did this particular project run? Um, 1 of the current controls and, you know, uh are there anything that we can be or should be doing differently? And so that's an ongoing process, I think that's part of that ramp up period that you know, I've been describing over the next 2 years, is how do we Implement those controls? Um, But yeah, I mean, there's there's still, there's still a lot of work to do. And I I feel like I you may have asked a second part of that question. I apologize. I was focused on the project controls. Well, that, that no. I mean, the question was how how do you plan to manage cost overruns better in the future? So which I Thank you via answered at least some of the some of the abilities you may have. Yeah, I mean, yeah, yeah, yeah. So it's, it's an ongoing process. Um, we are cognizant of it. Um, I do appreciate, you know, like I said, the icc's, um, calling attention to that. Um, it's certainly not lost on us, and, and we'll continue to work toward that. Now. I mean, the reason the cost overruns are such a big issue is, of course that they're they tend to come with a rate hike in, in the future and, and Miss moscowitz talked to, some of the, some of the ways that, um, our constituents are being, uh, crippled, by the debt they already have, do. What can you tell us about? Uh, potential future rate? Hike, uh, requests. Uh, and under what circumstances you would you would ask for an additional rate. Yeah. So um if you recall, you know, I mentioned right now we are evaluating the impact of that order as it relates to relates to our, um, Capital planning. And what does that do some of our operational budget, whether it's, you know, back office, uh, needs so to speak. Um, what additional labor costs? Um, that that would um that would require. Um Um, I do think that, um, as we continue to evaluate that inevitably, the question will be, you know, do we need to, um, are we receiving enough Revenue to be able to execute at whatever level um, and those amount of miles, that, that that may be necessary. So, I, I don't want to Discount the possibility of us having to go into the ICC, um, for their review and, um, their opinion on, you know what, exactly, um, a rate increase might look like Wasn't a lot of specificity in that answer but I think I, I will I will simply Let It Go on. I can understand why perhaps you you don't want to fully answer that question but I'm sure I won't be the last 1 to ask about rate hike. So I I'll go ahead and yield from there. Thank you, thank you Alderman Conway. Got uh, Alto the spot. I followed by Alderman Moore. Thank you so much chair. Uh, I really appreciate all of the presentations. This is something that like all of us benefit from learning about because at the end of the day, like our our constituents are both the workers and the rate payers who make this project happen. So I really appreciate the insights on both sides on this. I did want to ask about the balancing of priorities because Miss Boker, 1 thing that you spoke of both in. Writing in your words was the uh, about safety and reliability as the core components of your work. But then you also said that we need to prioritize speed Above All Else. Which feel like priorities at loggerheads with each other. And so I was wondering if you could speak more about how you balance those interests and also like, what are the the key roles and responsibilities of the safety monitor as part of all of this? Yeah, thank you for the question. Um, you are correct, uh, safety and reliability is Paramount um, above everything else. Um the the trick will be to balance that against that that deadline that's pretty specific in that order. Um what Um, what we are currently looking at, is that Jana model, um, and how it will help us sort of risk rank, uh, where the, the leakiest or most at risk pipe is uh, but then the question becomes is, you know, can we do that in in the time frame, with which we're being asked to do that? Um, that is still to be determined. Um, we unfortunately do not have an answer as to um how many miles that that will look like. Um, it is clear to us. I mean, the our takeaway is that speed seems to be the priority above all else. Um, you know, we had even evaluated, you know, what sort of construction would look like in 2025, um, if there is anything, we we could do at all, you know? and so um we chose to take Shelf ready uh projects that had been previously approved like I said before the pause that may look what look like what we can call is that um old SMP or do nothing at all. Um and so that's sort of the right now the short run balancing act that we have to ask ourselves but um, speed is, um, a consideration but against that we still have to balance safety and reliability. And that is really where the engineering piece and the uh Jana model uh, will will come into play. We think is that Jan as in Nancy or M as in Monster. N as in Nancy j a n, a j a n. Ah thank you so much because you've been talking about it now I didn't want to ask more about that. What do we know? What are some of the criteria that are built into that model? That determine the, the pipes that are most at risk, right? Um, I don't have the exact details of that. I do know that, um, when we right now, we are onboarding the the Jana model uh we will be holding hosting um 1 Workshop but we we are open to more um with our stakeholders but that will walk through on a more engineering technical level what that model does model does and doesn't do, I can share with you that internally. We are evaluating, you know, is there a way to sort of reprogram that so to speak? Um, that if we wanted to input something like an NPA, um, or if we wanted to, um, you know, Target a particular area or neighborhood first. Um, after that risk ranking, uh, prioritization, you know, what would that model look? Like I can tell you in some of the um uh during the preceding a lot of that modeling had included that old SMP stuff. When we you know thought about you moving meters outside and that neighborhood approach and also you know looking at going from low to medium pressure. Well, under the new icc's directive, we've kind of got to of got to reprogram that to conform to the icc's directives but also if there are other inputs like we mentioned, you npa's, um, is that possible? And if so, what what does that sort of new risk ranking look like Can you give example of some of the criteria that might be built into that risk ranking? I'm just trying to wrap my head around. Yeah, I I have to get you that. I don't have a specific again. It's a more technical engineering thing. I I don't have that today, but I'm happy to to to work with you guys. That's okay. Just curious. Um, I had 2 other quick questions. I was curious. Maybe this is a 3, the terror question, but is there a cost differential between the whole like pipe replacement and during doing the kind of cured in place that was being discussed? I, I don't have any information with me today about that cost, differential. I, I'm sure that we can get that for you, but I would need to talk to an engineering team and figure out that sort of design comparison. And what that might look like. I think, uh, Alderman, I think, uh, a scar might have some info on that response. Yes. And again, nothing is 100% all the time. It'll depend on the pipe. Uh, but I do think this is an opportunity for cost savings and I've just got a write up of the project that people's gases are already done. And it found that the uh, lining reduced the overall project, but it budget by 30%, shorten the timeline and minus minimize the disruption to traffic in the area. That that's helpful. I could you provide that to the chair Yes. Okay and I I say this because this is probably going to be a refrain in the room. I too am not an engineer. Um but like the the information that that's shared if that's valid. And if that is, those are scalable results across the city as we try to keep within this 2035. Timeline as we try to keep within cost parameters, it it feels like it could be a value and barring that. I will also say the last major people's gas project in my ward was along Milwaukee Avenue were you all actually did that trenchless model? Where they opened up pits at various locations and particularly for a corridor that is very Transit dense. That was very calm. Commercially dense. That is a model that was very much appreciated. By all of our constituents and businesses. Particularly as it was able to keep traffic flowing, keep both lines Lanes of traffic open and helped all of our businesses stay in business over that time period. So I, I really do appreciate a lot of the thoughtfulness and consideration. Oh I did have 1 other question that hydrogen hydrogen and that blending model that you were talking about? Yes, the idea that that could be a future model for zero carbon low emission heating, particularly in our kitchens is like the great concern for those of us with little ones The kind of pipe that we are currently installing or the cured and pipe. Do we know if that is compatible with this future concept of either Blended gas or Soul hydrogen? Yes, it's it's my understanding that it is. Um I I can say right now, you know, we're still going through that pilot. Um, I think that in the next 10 years or so, that, that is a technology that, um, may be viable in a larger distribution system setting, but we actually did, uh, test, um, a kitchen stove with, um, Blended hydrogen, um, and natural gas at our training facility and we're successful in, in testing that out. But, yes, they are compatible. Thank you. Thank you chair. Thank you. All right, Alderman Moore. Are you ready? Yes, I am. Thank you so much. Um, chairman and I want to um, before I before I get started, I just want to, since this is my first committee meeting, I have no idea. I have no doubt, this would probably come up in Council, but I just want to highlight and recognize the fact, um, that, uh, we lost a Um wonderful public servant um over the weekend and Lori Healey um I know my heart is broken, it almost made me want want to cry, even talk about it. Um, and uh, she was just a asset um, to this city. Um, a person who um, A person who represented this city well and uh for all communities, I can say that personally. Um, whenever you wanted to call, um, somebody in government, uh, whatever Administration she worked there, she was there to help you and I'm definitely going to miss her leadership um, in this city. So um my prayers are going out to her and her family family as well as the um, um, Mayors and especially the family who worked closely um, with her. Um, with that said, said, um, I just want to, um, again thank um, Everybody. Um, are coming um, as as president uh, Booking booking has come before us. I I want to thank um, her team, um, of Georgia's and Senate Wiki for bringing her uh, allowing me to meet with her and and get some conversation and get some understanding and I appreciate that, and I appreciate the work that you all do proactively to make, um, sure that we are staying up to date on a lot of things that's happening, uh, with people gas. Um, I was taking some notes and, uh, as we were talking and so for me, uh, I'm going to go a little bit out of order and back and forth, because I, I, I numbered them, as I was, um, talking to them, local, um, uh, 007, um, has spoken in it. Um, and I understand, um, they have, um, workers on this job and they said, it's and they are 80%, um, diverse 30%. Um, veterans. Could someone from their tell me? Um, how uh, how of those, where those workers, how many of those workers are African-American, that they have Alderman, Sean, Gorge guest. Uh business manager, guest workers out of the 80% diverse roughly uh, 40% are African-American. Okay. Uh make sure you provide that um, breakdown to me please um through the chair. Okay. Yes, sir, and and whole numbers and not just, uh, percentages as well. I know you wouldn't have the total, um, number. But, uh, please provide that, um, as well. Um, Also, are you all doing Outreach to high schools? This is going to be a long, um, process and are we are we doing Outreach to um, high schools that like Simeon, who got, um, trades, um, worker trade, um, classes there to make sure that this work force that we're still reaching young people and that they know about these jobs, um, coming down, um, The Pike Yeah, Alderman. Um, we are not a hiring Hall. We are an in-house Union, but people's guests, uh, has a fantastic program where they reach out to the Chicago, public school, students. They actually bring them in multiple times a year. And there's different phases of their training. And Saturdays are usually trained by 1 of our couple of our retirees that are 30 plus year, veterans in the industry. And they, uh, the companies does a great job in recruiting, Thank you so much. I I appreciate uh, um, your response to that, and I think you were prepared. Thank you for being prepared to answer that question, which states that you are um, doing the work. So I definitely appreciate that. Um, my third question comes around um, the report and when we we talking about safety and risk and and and I'm not going to sit up here and lie and say I read this whole report, um, and and I think, Conway stated something that I was going to say that, I I think you all probably got the lawyers and things like that to go through this because I wasn't totally clear on, um, everything with acceptance. The things that stood out with me, um, whether the cost overruns and I get to that later, but help me understand when we talking about the uh, the safety risk. Uh, we talking about to the workers or are we talking about to um, the way we, uh, the pipe that we lay help me understand that in layman terms and what the uh the the impact. of that is, um, both from a financial standpoint and a, um, whether it's a, the labor workforce or um, the operation standpoint because I'm not fully understanding the safety part. Is. That I assume that's a alderman Morris. Had a question for me? Yes. Yes. Because, uh, poopa gas or whoever can answer it. No, thank thank you for the question. I just want to make sure I wasn't, uh, speaking out of turn. Um, you know, to, to answer your question on safety. Um, you know, we're really talking about um, both Alderman Moore. It's it's ensuring the safety of our workers. Um, as they are working on the pipe replacement program and and certainly it's it's the safety of our residents and our businesses um, that um, that would fall under the purview of that. Some of that pipe replacement program, Okay and so what seems to be the issue around safety that the ICC was pointing out because I'm, it was such a big report. I'm trying to get to the the major concerns uh, within the ICC for um shutting this down because at first I had concerns about them, shutting us down and stopping this work because it impacted the work being done in our community and impacted workers. And so um, What did they come out with in terms was the safe, they just said it needs to be approved. What was the what what was coming out of that report around it? um, if I'm understanding the question correctly, I, you may be asking about the safety monitor, uh, which is 1 of the things that came out of the icc's order on February 20th and, and what that, um, that directive, um, the ICC will be selecting a safety monitor, uh, that will help, um, oversee the program. We're not entirely familiar yet with what their RFP looks like or, you know, um, if they put that out to to bid, so to speak and and who have been invited to it, I do know that the IC directs, the staff to select the safety monitor by July 1st of this year. Um, so I don't want to speculate but it, it may obviously speak to the safety components of what? What I just mentioned among other things. But the report didn't, so you saying the monitor will the report didn't speak to that for them to say that they need this monitor. Could you repeat that question, Alderman, Moore. So the report didn't speak to why the safety monitor was, um, It is coming out. Is it, is it something that they saw? I'm I'm like I say it's confusing to me, that's why I'm asking. Um, I I think I Question, I unfortunately, I can't speak to why the ICC may have believed or not believed that um, you know, a safety monitor was necessary coming out of the report that you're you're you're talking about. Um, I I don't have any sort of what that thought process was, but like I said, you know, it's it's in place now and um, you know, they they are to be selected by July 1st and and there may be some more information there. And that's why I was asking based on versus the labor and the operations because if we have Labor I think our labor unions. Um, Local 150, 007 are people who are concerned about safety. So are they have? Let let me let me start from the labor side. Are they saying they're having any issues? I mean, I'll defer to our labor Partners here. But yummy. Yes, we, we are concerned. As is our labor partners? Yeah, agreed. All the been marked all this local 150. Um, you know, we're we're concerned about the current status of the system. We believe there shouldn't have been a pause. Mainly because of safety, reliability and cost. Um, and and and and I'll I guess I'll I was going to chime in at some on this. But I I would just say that while we applaud the applaud the icc's current decision to reimplement, this PRP program, we disagree that the ever should have been a pause in the first place. And there's a lot of discussion about, is there going to be a rate hike in the future? I mean, just remember there was a long period of time where people's gas did not go in for rate hikes, they operated under the qip system through the ICC commission and recovered costs for a number of years. Other gas companies made the choice to continue to go in in incremental rate hikes. So this is only more recent where the um qip has expired, um and the sunset was not extended in Springfield. So therefore the only way to recoup cost is through the normal, uh, rate making process but I hope because I, I'm hearing a line of questions about or I think there's probably going to be more about whether there's going to be a rate hike, and there's going to be increased cost to customers. Make no mistake about it. That the cost of this program continues to go up for things like inflation. Wages benefits fuel costs, right? A number of factors that play into whether or not it's going to be more expensive. We spent an entire year at lower costs, not doing a program that should have been done for safety and liability. We're now going through a second year with a um a a a question in the era of what is the federal government going to do a tariffs and a number of other things and where are we heading as an economy in general? So I would suggest you that the cost increase is due to a number of factors, um, that are out of the control of people's gas. In addition to that, there is a major component of what the cost of gas is going to be going into the future and 1 of those things, I'll just mention is things like data centers. I mean, there's a massive proliferation of data centers, not just in the state of Illinois, but in this country that are sucking up a large source of energy from an electrical perspective, it's 1 gig from a gas perspective, it is 1.68 million therms per day that a large data center will actually, um, uh, that'll actually take uh to fuel some of these larger data centers. So it's a supply and demand type of a situation. So again, So again, you know, I I I hope that everybody doesn't continue to point the finger at a utility and you look at things like the Attorney General's office who asked for the pause. Well, I shouldn't say ask for the Pause, um, provided a detailed, uh, brief. Um, that would suggest that a pause was in order the ICC commission others that, um, uh, pushed um, for a pause to actually happen. So again, I just think it's misplaced to put the onent on people's gas that. Oh, there might be a rate increase when we should have all known that a pause for nearly 2 years is going to have an increased cost to the overall project. Uh, thank you. Uh, so much I appreciate that because that's why I was also going to go with this. And, and, and I'm that's why I'm to reach out in terms of the report because I was not in support of the pause. I know this pause is going to based on everything that you say it's only through even repeated that um it's going to be a higher cost due to um increase costs and and other factors. So I'm trying that was my question part out of this report and and maybe I'm not answering it right? Was there something that came out of this this report that said there was safety problems. It seems like that's a no was there was there something that came out of this uh report? Um, other than the cost which could be and it an issue that I want somebody also to speak to was it that um the cost overruns was it that um dramatic that it's going to be more than But don't cost overruns more than what we are going to see from this, pause. Does that question, make sense? Oh yes, um Alderman. If I um I'll try to answer that question. I I believe that the appropriate, um, let me reframe that, I When we talk about cost overruns, um, I think you're speaking probably more to the um, the allegation that there has been uh, past mismanagement. Um, I believe that that is separate from the question of of are there going to be increased costs due to some of the things that Mr. Pulos has talked about some of the things I already know. I'm sorry, I don't mean to cut you off. I know the answer to that. There's going to be increased costs but I'm talking about. So the cost overruns wasn't proven that was a statement. That's what I'm saying I couldn't. That's why I'm trying to really get into the and understand this report in layman's terms. So I as I'm talking to my constituents, I can explain this. So it's back to my questions. I know that's going to be an increase, and you may not have that number to what that increase going to be in the impact is going to be for us, waiting 2 years, but I did the report talk about what the impact of those costs overruns were from a dollar standpoint. Oh Alderman Moore, I this is this is chairwoman chairwoman Manhattan um 1. I I do want to get we've got several other committee members who have questions and I want to be cognizant of time but I I think I think they have all answered. Questions about this. I do want to point that um while this program was paused, um there was work that was allowed to happen for emergency repairs. There was I think 28.5 million authorized for people's gas to do work. So it's not like nothing happened. Um, and I will say that as you talk about some of the safety pieces of folks, want to dig into dig into the report. Um, uh, I don't the ICC did not make this decision lightly. Um, you know, Mark's points are are well taken to things are getting more expensive period. They're getting more expensive and and I think that the people's gas is also kind of making a note here of there are costs may go up. There are costs, that will be um, Uh, there are costs of this program as they move forward, and we the rate payers are going to pay for it. Right. And I think that's why we've got the panel that we have here and this is a you know we've got the utility that that is trying to do better and and meet their goals of safe delivery of gas. We've got the the labor Partners who, um, I think always make safety Paramount in their work as well. And we've got, um, Our consumer Advocates and uh also thinking about that rate payer piece. So I don't know that there's more, they can say to that, uh, they can't predict the price is going forward. And what we do know that we're going to see as some people have brought up um impacts on this work going forward 1 way or the other. Um so if you could I don't know know if you've got another question I do and I'm going to wrap up but I could have gone. Last, I would have waited I'm not a committee but I was called upon. And so my thing is I'm I'm not asking about as much as the rate increase in a way that other people are. I want to be able to explain to my constituents that when they do come I need to know need to know that the impact from whether the pause and about that pause which I wasn't in support of and I don't don't believe that total part should happen. I understand everything that you say it. And and then I and maybe I can talk offline with, uh, people's gas on it. But sometimes this stuff's got to be on record and understanding. That, that pause could have have a greater impact than what allegedly those overruns are. And if those overruns are real, I want to know what those are as well. So I can, you know, be able to, um, speak to that. And that's what I was asking about. That's a different question. I got, I got you. And talking about just rates and rate Heights. That's a different question under understood Alderman, Moore. I think you should really dive into the report and that might be an offline question because it's going to come down to opinion, right? So, I see decided that It was most important for the Safety and Security of the program to pause. Because as you can read in the report, they found a lot of mismanagement that were leading to um ultimately higher costs for the rate payers, right? But you've got people of differing opinions here so I don't think you're going to get a, a pure answer, you've heard the opinions. Um, I'd encourage you maybe to reach out to each of our guests, if you want to talk more about that offline, Okay, and and thank you for that chairman. I appreciate that. And my last question would be, because, as we talking about increases and this may be a long, those lines too. Chairman is my last question and uh, oh my last 2 questions. Um, the, the it when we talk about the right to sort of like, when we talk about property tax appeals, right? When we have, when we have Um, businesses commercial businesses closed. We absorb the all the the the property owners, absorb more of a property tax increase because we lost business is, is that also what's happening as we're being pushed and, and and places, I've been pushed more to electricity be a buildings or a household, are then more people absorbing that cost um, of gas because we still got the piping and we still got the the same pipe and the delivery system that has to go. Through. So it is is that part of that increase as well? Um I I appreciate the question. Um I I think what we're getting at is, you know, is it possible that there is an increased cost to uh those um, rate payers still left on the gas system? If if they transition away and and the answer is yes. We we believe that there is, um, a financial impact, um, to, uh, those rate payers to their detriment. Um, I, I hope that answers the question. It does. And then that's why I just want us to be cognizant and get this conversation out because it's important. And then my last 1 is to, uh, people gas. And maybe you can provide this, um, through the chair. If it was given to me before, just resend it. Uh again a lot of money going on here. We talked about jobs. Um how many I want to know how many? Um, African-American contractors, we're using on this job. If you could provide that these jobs, I if you could project that through the chair We, we can get that through, uh, through the chair alderman. All right. Thank you so much and thank you. Um, chairman for allowing me to, uh, chime in absolutely. Thank you Alderman, Moore. All right, we've got all our sick. Joe Lopez folder by Alder Lopez. Folder by Alderman. Reilly. So we'll move on to um, Alderman Lopez and we'll come back to Alderman sigil Lopez. The original. Thank you. Chairman and that'll be the last time I ever let David Moore. Go ahead of me. But good morning. Um, yep. Good morning. Uh, committee and good morning to our guests. I just have a couple. Um, Pages of questions and things to talk about. Um and thank you to all our colleagues for some good points but I just want to bring up a couple points if I met chairman We need to learn from history. Here in this room. And in this building, um, because as we look at the pause, that happened with people's gas, thanks to the state, uh, Illinois's the state's Illinois, Commerce Commission, I I I have flashbacks of the Uh, lead line replacement. That we had going on. That was for a few years, a very robust program and then came to a screeching halt. In our communities. And over something very simple in negotiable. Whether or not to go around a tree. And as I'm looking through this 293 page document, which I'm glad to see my colleague from the 34th W read. Um, I see a lot of finger pointing but at the end when you finally get to page 236 2 years worth of of of bickering posturing, and politicizing. And we came back to the same conclusion. Get back to work. But now we have to do it. 10 times faster. Excuse me, 100 times faster. Excuse me, because it went from is it says on Page 6. It went from. Roughly, excuse me. I lost it. 4. I think it was 47 miles per day or something along those lines. 49, thank you to now 110. And that's assuming that we are at 100% Optimum capacity on day 1. Which as we heard today is not going to happen which means the more more likely going to have to be closer to 135 miles. Once this 2 year Hiatus kicks off And while we're talking about the rates and everything else before we get to people's gas, the city and ourselves. I I just have to go on again with, with regards to the ICC. and as they are talking about, Rate increases, and they're talking about the impact on on consumers. They didn't bad an eye in 2024, adding a 624 increase on businesses. uh, without any kind of impact study, or to see what that's going to do, to the mom and pop businesses throughout the entire city of Chicago, a new search charge, which my residents have told me that this equates to $22 a month for struggling businesses throughout all our neighborhoods. Now, I understand where the money is going, it's going to help the low-income the low-income fund otherwise known as CEDA. But as we're talking about the impact, it's not just what icc's doing in terms of allowing people's gas to charge more for much needed repairs but it's also what they're doing on top of that to our struggling businesses. And I think that's something also worthy of a conversation in this room. I do thank people's gas for being here and, and assembling this team that's been at our beck and call. Um, but I think it's really unfair. Uh chairman and members of the committee. Um 1, I look at time and time again, the city's position, always seems to revolve around insufficient data, wrong cost, estimates this, that and the other, and I've been trying to like 1 of our other colleagues. Look at this Janna, uh program. Um, I'm not going to go into it because I think it's, it's still a work in progress based on its, uh, what I've been reading. But I think we can put parameters in place that help reduce and, and streamline how we do things. But the interesting thing for me, ladies and gentlemen, is that the same thing that we're asking of people's gas to do, we don't even ask our own departments to do. The same thing that as we have seed Dot, and forgive me, a Deputy Commissioner, but I'm going to point right at you in a minute. Um, I've seen where we've tried to coordinate departments to work with utilities, to try to help our communities. And when we look at, Time After Time After Time, where it's listed the cost estimates. are not, uh, actual, or Consistent. We could very well be talking about C Dot. Our own departments. because I've seen where on blocks in the 15th Ward, where we used to have people's gas doing work, we try to coordinate with C Dot and people's gas to do some of that sidewalk replacement to augment some of those menu dollars and when I propose that we do full-scale Replacements alongside our peers or even our use menu to pay what they were going to pay for their restoration. I was told I couldn't because our costs were nearly double what their costs were for a sidewalk. If its 40050 that they are paying, we're paying 900 for the same tile. Our costs. Are just as inefficient and and estimates are as undefinable as what we're accusing. People's gas. There's plenty of work that we should be doing. but I think that for as someone who grew up on the southwest side of Chicago, I can remember the dangers of having work happen or not happen. We've seen how I've seen houses explode. I've seen a block explode in front of a church blew out all the windows in a church on the southwest side and what is now the 23rd Ward. We need to. Focus on getting this done. We need to as a city, look towards things that we can do and I appreciate some of the Advocates and other folks who come up with suggestions and and things and concerns that we're worried about. But I think all of those can be mitigated because when we look back to page 236 there's actually I take that back when we look back to page 238 what is ordered by the commission There are definite calls to come back to the table to work together to put workshops together and I know people's gases offered to do those with our advocates. But at the same time, we've got a job to do. Ladies and gentlemen, they've got a job to do. And when I think about all of the need that's out there in our communities, when I hear that, we're trying to find ways to put people to work, who wouldn't want a 10-year jobs program in effect, that's hiring from our communities. That's overwhelmingly. Inclusive of of those that we always say that we want to see represented in these opportunities. I don't want us to get bogged down. Madam chairman in. Trying to demonize a utility as we're trying to find ways to evolve that utility. We're not going to beat Evanston who now has a an all gas retro uh gasless retrofit ordinance you know that's just going to be Evanston Chicago is Chicago. We can be Swift and we can be Speedy while being safe, while being safe. They are not incompatible. and I think that I have full faith in our friends and labor to get the job done quickly, uh, as required by the law, which by the way, if I'm not mistaken, there's no relief from Springfield either on this matter, correct? No. so, for all of the grandstanding that we get from Springfield on on, Why this was necessary? There's zero support to get it done so it will fall on our taxpayers. But we have to invest in our neighborhoods in our city and if it's every hundred years we are ourselves are doing that right now. Ladies and gentlemen We've taken out billions for infrastructure Replacements, to fix the bridges, to fix the roads, to do things like that. We're shutting down Bridges right now. Because as commissioner Carney said, it's over a hundred years old. And after 100 years, you have to replace things That's exactly what we're trying to do. And I believe, if I may be so bold. That this isn't going to be the end. That this isn't going to be the last time that we're doing things like this, but I think that there are plenty of opportunities to, for us to move forward, Madam chairman, uh, as you've already alluded to that, we're going to have yearly. Meetings with uh people's gas and I know they have been coming here. Um, For years, even bringing us a few years back that corroded 2 inch thick pipe. If you recall They've always been willing to show us what the problem is. We need to show them what the solution is on our end. And what I would actually challenge this committee. Chairman Is to. Address 1 of the issues that we've seen when it comes to this work and the scope and maybe allow us to do better coordination uh, between the utilities and our departments. Is that on average we have roughly 25,000 give or take um permitted events by people's gas in addition to all that make up not only what are the emergencies? But also that I'm sure we'll be inclusive of the 110 miles that we're going to see. I think a good faith measure by city council. Would be a simplified permitting process. Once we know what the scope of the year's work is going to be for example, if we know that in 2026, that they're going to have 110 miles worth of locations that are going to require permitting for the whether it's the Full replacement or some other thing. Why don't we have a single permit? For that year so that they don't have to sit here and waste time with C Dot and all the other departments going after these individual permits. Time After Time. There's no Expediting of these permits. There's no rushing of these permits. And if you really concerned about bringing down the costs, then a unified permitting Pro, an annual unified permitting process is what, uh, I think is an order for our utilities and I would make it open to both utilities as a matter of fact, but I think in this case it's more pertinent to what people's gas is doing. And so with that I would ask um people's gas um, how much time? On a particular. Project. Is spent navigating a permitting processes. Thank you for the question. Um, In reviewing some of our historical practices that I had mentioned earlier in the remarks. Um, we've sort of taken a sampling of, you know what that process might look like. Um, the That can be anywhere from um, from design to permitting. Um, let me give you a flavor for the design process. Um, it's it's my understanding under rule, it should take days. Um, sometimes again we have the coordinate with a lot of different folks uh that can uh take as long as uh 6 or take as long as uh 6 or even 8 months. Um, after that that design is only good for 1 year under the current rules, uh, to move on to permitting, um, depending upon the size and upon the size and scope of a particular project that we are working on. We will then have to pull a series of permits, uh, that also have expiration dates, um, and I'm still familiarizing myself with, uh, sort of that 1-time renewal option or whether it expires. Uh, but, uh, we would then have to go back in depending upon the expiration of those permits, um, to be able to come back and, you know, continue on and roughly speaking. How many times has people's gas either not gotten off the ground in time or had to either seen a permit expire and then reapply or have to get an extension on that permit. Um, those numbers do exist, it has happened. Um, I can get that for you but it, but it, but it's, it happens. It's an event. So, and if you could provide that through the chair, I would appreciate that. Um, and then the other question with that as well, is the subsequent costs of missing. Those marks is also Something that is not something necessarily planned for, but it is a cost that has to be borne by you, and ultimately by consumers. Correct. Yes, that is correct. So I think that is 1 instance, chairman where if we're looking at Common Sense ways to help, Do the work while also ensuring that we are. Being respectful of the money that ultimately will be asked of our our residents and their customers. You know, those are the types of things that I think that we also can have a direct impact on and I would be happy to work with you and whomever whether it's in this committee or it should be I think should be in this committee or jointly with Finance to see what we can do to try to alleviate these. Pressure points. These choke points. If you will in getting the work done, if something is permitted. On my block. 43rd in artisian and they missed the Mark, it's going to cost them thousands to try to redo it simply because Something may have happened the fact that it takes 6 to 8 months for us to get some fee finality, for them can literally say that if they applied today, they might not make it by the end of this year because of what this city hall, departments are doing. That's unacceptable. So, I think that if we could find a way to address that concern, that's just 1 point. But if that is an area that it's replicated, even if it's a thousand times, a thousand times, for thousand dollar permits, there's a million dollars. Um, so I'm wondering just along that line of questioning too if uh, seed out would like to weigh in, um, just in kind of of same question that older Lopez had asked, but if you could speak a bit to permitting process and, and I will say, um, Alderman Lopez to your point, um, Obviously it is an issue, right? I I would agree. It's an issue for them because we see reflected in the report that sometimes C dot would be actually 1 of the problems was people's gas, uh, inappropriately using the ability to have emergency work and kind of circumvent permitting processes to get work done. And I would argue and I think this is the city's position. We try to work towards compliance if somebody is gaming the system or inappropriately using a system, typically it's because they're trying to solve a problem. And so either way, There's a problem. What can we, what could we do to improve upon it? But from the C dot piece, if you could speak a little bit to, um, working with people's gas on permitting. And, um, whether uh, something like a unified permitting system is something we, uh, the department would consider. Yeah, this is Jal with sad. So this is something that may never came up before as a unified year-long permit for a blanket permit. That is something is blocked by block, you know, we see that will lose control of that. So some something that we could look at it, but the coordination piece so there are Uh, utilities underground. Our right away is full of utilities. So that's what we do, coordinate with all the utilities. So, the coordination process and somebody else comes in in between, so that's why we have a yearly limit on that time frames on it. But, if, when is a resub middle, you looked it up and it is a much quicker process. Do you have a follow-up? Sure, thank you. Um, A couple things first off this was proposed. Um, In the last Administration by yours truly. So, I know it has come up before. Does the util do the utilities uh contribute to the OU? Yes, they do. How much do they contribute to the OU which is the under the office of underground construction. So, utilities pay with the uh City of Chicago is only 1 entity within the oec so OC's office management is run by the board. So City of Chicago is 1 and in addition people's gas support. When they have major project, we have a coordination supporting agreement with people's gas, and they pay for Additional can you provide through the chair? How much both utilities have provided annually for the last 3 years to the OUC? Sure. Could do that. Um, but I think chair, uh chair, that explains even still. It doesn't change the fact that we need to find ways to make this. Move faster. And if the OUC is is lagging for a lack of better expression, then we need to find ways to make this move forward, their plans. Nothing is changing Underground. A pipe is a pipe. It's not, it's not moving, it's not going anywhere. And if they say today that we need to replace this pipe odds, and they don't replace it in 8 months, it's still going to be there. We shouldn't hold them. Hostage or liable because the city doesn't move. And I think that's you know if we want to truly have a conversation about how we as you said are addressing the things in this 2389 339 page report. That's what we need to be focusing on. So again, I look forward to working with you in the Departments to make that happen. I think that uh if we want better estimates and we have to if we want to bring costs down through better estimating then we have to do our part 2 and that's 1 clear way that we can do that. Thank you, thank you and uh recognize Alderman, O'Shea. Um said non-competing member, thanks for being here. And I've got a quick question before we move to Alder sik, chol, Lopez and Alderman, Reilly, and, and just along that line of thinking. And I know, um, When will people's guests have a plan? so, thinking about a, A Time certain. So you guys are, you guys are working on this. You're working on the short-term piece. I know some of the questions solder and Martins uh, uh, response to solman. Martin's questions were a little broad, but I imagine at this point, you do at least have some project management goals of like, when you will have a plan, um, so to Alderman, Lopez's point, if the city wanted to coordinate, right of like, hey, there's a 10 year time frame. You really, you know, 9 years we have shared goals of wanting to make sure that right like the the Most at need work gets completed, you know, that's about 1100 miles. You know what that pace is have to be, there are a lot of known variables, um, that people's gas and your partners have. And so, you know, I think it's fair for people's gas to ask the city of Chicago for assistance and saying, hey, what could the city of Chicago do to help make sure that we can complete this work based on this time frame. But I think 1 of the things that we would need to know. Is, when are you going to have a plan of like, hey, what is what's your goal for 2025? What's your goal for 2026 and then what is that 2027 through 2035 plan look like, so can you tell us when you think you're going to have the details of that information? Uh thank you for the question. Um, I will say right now we are still working through that. Um I would say earliest estimates it possibly look at quarter 1 of 2026. Um again we still need to sort of recalibrate that Jana model. Uh we do want to offer our stakeholders an opportunity to weigh weigh in on anything else that they believe we should be prioritizing. Um, obviously I think if we do some very easy, you know, back of the envelope math, you can easily see sort of what that mileage might look like in light of the time frame. Um, we have already begun discussions, like I said, with C dot about what that? Potential run rate, looks like no plan, but just, just even that number. Um, in order to sort of get a temperature check is, is there anything we can do with the current Frameworks that that we both have today on C Dots part? And And with with pgl, um, are there things that we can do? That might help expedite that we've had 3-way conversations with, uh, water and sewer about us following them them following us. Is there an appetite for things like a pilot program where we could test out some of what Alderman Lopez had talked about? Those are all in the works, but to answer your question that plan we're hoping is starting to take form early 2026, so that we can begin that design process that, I sort of described. Okay. Um, so it sounds like and Alderman Lopez not to not to call you, so it sounds like they're having some conversations. Um, I think it would be helpful. And maybe you know through um the committee we can follow up with the water department and with C dot. Um but Ultimately, I think coming from the council piece of us not being the experts and I'll chime in on the, not an engineer piece. Sure, why not? Um, we're not the engineers, we're not the experts on this piece. You guys in our departments are going to be and what's possible. Um, Alderman Lopez, I think what I'd be looking for is a proposal Right. Like what's, what's the pitch? And so if there is something that, you know, people's gas wants to ask the city departments to do or a slate of options, um, I think it would be worthwhile through the committee for us to work on that and discuss it and would just, you know, we get busy, we get sidetracked. So that's where on the time frame of what makes sense for your time frame within the city's time frame. That's where I look for more of a Time, certain of, like, hey, when should we follow up with you about that? Understood and I would definitely want to work with um Mara here in Michael about getting um that timeline to them and then working through those appropriate Channels with you guys. Okay, almond Lopez. Thank you, chairman for giving me. Um perhaps it's something something that we could work on together, maybe even if it's a call for hearings, just to see who all is impacted by the OUC and and the permitting because I think it that will do a lot to save, not just people's gas. But many of even what we do even our own menus, often times we hit snags on this, so happy to work with you and your team to figure out what we can do because I think that will answer a lot of questions here in the committee. Thank you. Thank you. All right Alderman sigil Lopez folder by Alder Reilly Thank you, chairwoman. And I appreciate the the, um, the timely matter for this hearing is, especially with the um, public security and these specific um, effort by people's gas. Um, I just want to talk about the the cost associated with this. Um, I am I'm personally concerned about the the the budget associated with this and the, the many changes that the budget has reflected. Is my understanding. Is it correct that? Um, is there a 7.2 billion dollars left to complete these? Um um uh this uh infrastructure. Uh, renewal project for people's guys? Is that correct? um, Alderman, sichel Lopez. Thank you for the question. Um, I think what you might be referring to is, um, in in the preceding during the 13-month review, uh, people's gas had provided a range of estimates under the old program. Um, obviously, you know, under the new accelerated timeline, we had proposed a different timeline for completing the project as originally proposed. Um, under the new icc's directive, you know, we're looking at a 20 to 35 deadlines very different than what we proposed. Um, obviously we've spent a lot of time talking about some of the potential resource constraints and so, um, I would anticipate that there would be a significant cost increase um under that sort of constrained timeline. Um, and I think Alderman Lopez kind of highlighted too, and that, that's assuming, you know, it's running on all Pistons perfectly, uh, no cost overruns, no permitting delays and we're really meeting that deadline and we're getting to actually retire, um, every mile of of that 1100, mile mile, uh, milestone. in terms of, so, there was a Blog called article report that Show that in people's gas uh, in the last 14 years, they only replace about 40 38% of the of, of the pipelines. Um, that's what the, the the costs that I am referring to. Um, so because we, you know, more or less, um, spend 3.3 billion dollars, uh, in work that has already been completed. So is the work pending and I think that the concern that I have is Because this increases go and are paid by the consumer. Ultimately, are the customers that are paying for this my own, um, looking at different, a different. Um, um, Sources for this, but it's about like a 6 dollar increase. Um, pay, um, per bill for Conns consumers, is this accurate and also In terms of, I think you're making a case on a reduction of the time frame, but that's 1 of what the recommendations of the the ICC to resume this. So if you could, if you can explain why like how How is a fair for consumers, uh, to pay for continued to pay for future work? Um, just given the history and the track record of of, of the delay in the work and the recommendations of the IC itself. Yeah, thank you. Um, as far as the 6 dollar increase, whether that's accurate, I I don't have any information that could speak to that. I would want to go back and try to figure out kind of, uh, what, what you're referencing there, and I'm happy to try to answer that for you, um, through the chair. Um, on the fairness question, I I would just ask for the opportunity to reframe that. Um, I think that, you know, when we think about the pipe replacement program, this is really not a fairness question for us. It really is about safety and reliability and that's something that we don't have the luxury of foregoing. Um, we have to replace the pipe. Uh we also have to follow the compliance of the icc's direct. Effective now, will that change over time, uh, from the ICC as it continues to monitor us? Will the safety monitor weigh in that? That's possible. But unfortunately, we don't have the benefit factor of foregoing these necessary upgrades and improvements that are required to keep every Chicago in safe. so let me, let me refer them to these, um, another another figure I think as of last year, maybe more recent, again, from a block club, uh, article because uh, customers already saw a bump of about 10% per bill, which is a record high, a total increase over hundred million dollars total. This was a an a study from last year, but the same disparity mentions, you know how, uh, especially seniors and low-income families, the struggle they've been neighborhoods where, uh, reportedly as many as 16% of the total population in that neighborhood. Uh, has seen now a, a a risk of not of of seeing their uh, their line or their, their service being suspended, you know, and these are families that rely on this. So again with all of their is being asked from the consumer. Um I think at 1 point you know, what is the the the company doing to rectify to show? It seems like in some cases they are Our programs available for low-income and seniors. It seems like it's a, a, a awful, a lot of them and this is a huge. this is a huge infrastructure bill is about 10 billion dollars total write independently, how, and the customer change. But I think this is a front by the customers. That's my main concern. So there's not a concerted effort, I think like you said, it was a ten dollar just as last year and this increases continue, even though the service and I tell you from a family from more neighborhood, that had a car in their service that talk about people who rely on this service during winter time and it took us a long time to get getting the service back, right? So, I am really want to see how as a company, right in the terms of like this is a very profitable Enterprise is doing to help those Chicagoans again. I'm talking about 16% in some neighborhoods that may not be able to pay. But yet we talk about billions of dollars associated with these infrastructure that they would pay on front. Yeah, thank you for that. Um, first of all, I I do want to set the record straight that we do care about every single 1 of our customers. It's not lost on us that um our customers are your constituents and we we understand that um over the last several years, people's gas has contributed over 15 million dollars through its own shareholder dollars towards um, a program that we call share the warmth. Um, we also um, uh, have the light Heat we share the same concerns as um, citizens Utility Board. We are very cognizant and we are following, uh, the fact that this new Administration may be um, cancelling and wiping out Li Heap and in fact, just last month, our credit and collections team, uh, went hand in hand, um, in Washington DC, uh, with some of our consumer Advocate groups in order to, uh, Lobby for the retention of of Li Heap. Uh, the other thing, too is I will say that uh we are 1 of the few utilities that did not appeal the low-income discount writer uh to the state of of Illinois. When that was implemented by the ICC. Um, we came up with multiple tiers that help some of our most vulnerable communities in which we serve. And the last thing I would say is, um, just last month. Uh, I myself and my regulatory team. We did meet with the ICC and we proactively aldermen are flagging. Um areas of concern for us on that affordability issue. Uh, we've invited the ICC to, um, be a partner with us and help us through that dialogue. And help us be proactive about how we flag that. With that being said, I also want to set the record straight that I think that it's easy to maybe look at At some of our costs in a vacuum um, our costs as a natural natural gas utility are some of the lowest in the United States. There's a couple studies out there again, happy to share them with you. Uh, 1 for example, um, the city of Chicago and our natural gas, uh, Bill ranks number, 16 out of 40, major cities. Um, we fare better than New York than Washington DC, um, in another study, uh, Natural Gas, Utilities are ranked second lowest in the in the entire country for the state of Illinois. Annoying uh, second only to the state of Wisconsin. And so I I want to put that into context because I think what sometimes gets lost. Um even though like I said we we are very cost-conscious about what this program might look like we are very aware. Um everything is going up the cost to borrow to purchase your first home. Um, a carton of eggs, a gallon of milk. Um, electricity prices are on the rise. Uh, we're very aware of that, um, and we're doing everything we can, uh, we remain open to ideas on on how else we can best support our most vulnerable communities. Yeah, I think. And and look, I I I um, I tell you that for many Chicagoans today, you know, the the the the the the cost of um electricity is is um is is is um is is almost out of hand. I mean we look at these report from block Club. You talk about like low income families. This is in particular a story of a senior who um basically saying that saying that he cannot even sleep at night with that. That thousand dollar debt that they have. Um, I think I'm, I'm, I'm really concerned about infrastructure bills. I think the ICC and I'm glad that this was put on hold so that we can have uh, as serious discussion about the the whole project. I mean, in this same article, some of the some of the users are even talking about. They would rather move to electricity the to Electric um um energy. So I I'm I'm talking about the tremendous investment that is being on front. By by consumers, right? And the little programs especially low-income uh, families are able to receive, they see the project a programs and so other have not kept up with the demand. And again, I mean, 16% of people who cannot uh, afford the uh, the utility is a huge number. I mean, these are people who are really now struggling and in their own reporting, they cannot sleep at night because they don't know how they're going to pay. So I will, um, share. I will, you know, um, um, Ask us, you know, continue to look into this issue and I'm really concerned about the the the the scope. The magnitude magnitude of this program, how consumers? I I'm fronting payments and the Alternatives that we have. I mean I think think to us, I think I spent I mean my office spend um weeks trying to resolve a case. Uh, we basically we even struggle to get some of the some of the um credit for pay for pay for service that they did not received. I mean, I think this is, this is I'm talking about billions of dollars, I am talking about people, consumers customers on fronting this. And, again, the, the Alternatives that we have to go to clean, sustainable and affordable options. We cannot afford to leave people without Service, uh, during the winter time and so forth. So, and I would like to explore again. Another, I know 1 of the panelists mentioned, maybe not for this hearing that there's been frustration with this program in general. And I do agree a thing on this and we did definitely need to talk to the ICC as a community, to discuss our options. Because affordability reliability, as well as the The clean uh, nature of these energy. I do think is something that should concern us all. Thank you chairwoman. Thank you Alderman. All right we've got Alder. Reilly and followed by Alder Taylor. Thank you, madam chairman and and thank you for uh, having this hearing today. Um, I'd love to get Commonwealth Edison in here again soon too. Um, a lot of my questions were already asked I I I do want to react to some of the testimony that I heard from the box today, um, you know, while I appreciate some of the recent studies that show, um, in context, uh, gas bills in Chicago, are lower than they are in some other big cities around the country. Um, I'm glad to hear that, but I think that, that local consumers here looking at their monthly gas bill, Probably aren't taking a lot of solace in knowing that that customers in other cities are paying more than they are. Um, to be clear, the gas rates are soaring. And and frankly you know, it's likely another rate hike is coming. Um, hearing that 16 to 18% of customers are more than 30 days behind. On their bill is is also a grave concern. Um, and there's nearly hundred million dollars in Consumer Debt here owned to this owed, to this utility. Um, you know, this has a disproportionate impact obviously on lower income, families and families of color. Um, and now we're hearing from everyone here 1 thing. We all agree on is that lip is grave risk. Um, and the low income heating assistance program, uh, is a critical circuit breaker. Um, so thank you to people and to Local 150 and to the consumer advocates in the Box for hopefully, working together in, in concert to try and save that very, very important program. Um, I think that would be an absolute catastrophe, um, for consumers, here in Chicago. um, you know At the end of the day, look I look and I know that labor costs are what they are. um, and I understand that that Commodities, you know, those prices are sensitive. We've been dealing with inflationary inflationary costs in recent years, um, and have not gotten relief that we'd hoped by this point in time. Um, but you Um, but you know, that plus the threat of the, the Trump, administration's tariff program, you know, he's he's hell-bent on on igniting a trade War a global trade War. Um, I worry about all those cost inputs that go into this. Um, and I'm going to talk to seed dot here in a second. But it's also not lost on me. That. People's recorded a record profit last year. and so, while I understand, You have to go procure, your gas at the rates that are available and that you're not allowed to Tinker with those as you transfer that cost to the customer. Um, when you made your your rate case back in 2023, You looked at the ICC dead in the eye and you said not to worry here. Our request for increase in delivery costs. Will be obviated by. Will we predict will be much lower gas rates? Um, and that's not at all. What happened here? Um, consumers looking at their bill this month. And comparing to a bill last year and it's 103% higher. Um, and we learned that people's is doing really, really well financially, congratulations to the company, you know, I mean, that that's great news for you. Um, and I'm not rooting against people's profitability. But I do worry about the impact on the end consumer here and this is not the flavor of the month. For me, this is something. I've, I've been very consistent on since I came to this body in 2007. Um, I used to do some work for you, utility companies here in the state of Illinois. So I'm familiar. Um, with rate cases and the ICC and how costs are calculated and how they are reimbursed. um, and so in light of all of this, um, I'd like to know on the record if people's gas plans to petition the ICC. For a a rate increase in 2025, are you are you going to petition the ICC this year for yet? Another rate, increase. This year, we do not plan on petitioning for a rating increase. How about 2026 that is what we are looking at? um, I don't have a definitive date Alderman but yes we are looking at where when when do we go in and part of that is you know obviously I think um chair hadn't spoke a little bit already that that is part of that planning process trying to get our arms around what what is the size and scope of what's needed? Okay. Um, you know, I I would just caution the company, you know, this body members of this chamber have been approached by a number of consumer Advocates, and an environmental groups advocating for a, an accelerated electrification program here. And I know that Consumer Advocates and environmentalists around the country are pushing this, not just, you know, States like Illinois. But Everywhere. Um, and I just a note for you all. um, you know these Perpetual rate hikes Feed the appetite of those of those Advocates and consumers, frankly, looking for some sort of rate relief, competitive relief. And I know there are all sorts of issues wrapped up with electrification often. Sounds a lot better than it actually is um whether the capacity exists to offset taking customers away from Gas companies like yours, all of that. Um, but I'd say, you know, the way you slow down those efforts and those campaigns. Is to show consumers that they don't have to count on a massive rate, increase every other year. Um and so I think you know 224 million dollars in profits great um for you. Um, it seems that there's got to be, there's got to be some float there, where, maybe perhaps the consumer can get a bit of relief too. Um, and that's my primary concern here. Look, I know you're a major driver of jobs and investment in Chicago and I thank you for that. Um, our partners in labor here uh are important to me and it's good to know that they're getting all of this good important work done. Um, but consumers need help too. Um, I wanted to speak to the the seed dot issue because that's 1 that bothers me as well. Um, pertaining to the OU and also how long it takes Companies like yours to get permits pulled for this important work. Um, and I didn't get a really um, clear answer from seed dot on. Why we have some such substantial delays, you know I'm of the mind that we we definitely need a better process and 1 that's much much faster. for the Utility Partners, whether that's people's or comment or anyone else AT&T whomever, Um, but I do know that part of that. process for issuing, a permit involves checking in with some of the local stakeholders, including the local aldermen, to make sure that information is properly disseminated when say 3 blocks of traffic are going to be shut down for an extended period of time to allow for um, restoration work to occur. Um, So maybe see dot. Let's get you on the mic 1 more time here. Um, Could you explain to us? What factors into these lengthy delays? Because I remember, you know, under mayor Emanuel which seems like a million years ago. Um, we had made some progress and coordinating, um, getting private utilities into our trenches. When we knew the city would be doing significant either water. Uh or or other type of work under the public right of way. And I remember hearing from companies like yours at the time that this was a welcome change and that it was making things more efficient speedier, um, and I would suspect probably saving a little bit of money on along the way. Um, what happened to that program? Because I could tell you someone who represents a big chunk of downtown. Um, I'm seeing utilities opening up my streets over and over and over and over again in the same calendar year. Uh, especially in River North and in streeterville. um so maybe C dot could explain that a bit so the OUC process is uh, simplified and they that all 30 members that respond within, uh, 30 days so they are very good at responding on time when a conflict conflict get arise between utilities, that resolution is 1 at time. So what you see so happen, all members, sign off and say that. Yep, the utility this based on this plan, this will work. It will protect my facility. Ities. So that conflict resolution is the ones that that is between that designer. And the conflicting Department comforting utility. So how sad can I fix that issue? So that's something that we've been working with that uh, utilities. Once they have a resolution comes in there. We tidied up the timeline to you need to respond. I don't understand. Could you repeat that slowly please? so when whenever when a conflict identified and the project owner resolved, the conflict then they resubmit we tighten up that timeline to 7 days then the utility have to respond back within the 7 days. So it is is basically the conflicts are the time delay happen. It is, is in between the project owner, identifying that once they identify the conflict, resolving the conflict. Okay, that sounded very bureaucratic. Um, not sure. I'm excited about that answer. Uh, you know, uh Madam chair. I I I had some more editorial comments. I was going to make today, but I think I'm going to save those for another day. Um, I would like to hear back from people. So, when they have a better sense of their program, whether or not we can expect another rate hike to be sought in 2026, Um, 2023 delivered, a hundred million dollar rate hike and I sure hope that's not another um, prospect on the horizon here, um, because consumers are getting crushed and I'm not saying it's people's fault. um, Every single cost people look at monthly um on their kitchen table when they're paying their bills has gone up significantly. And so I'm just going to say it 1 more time. Um, the city needs to do better, In getting you uh the permits that you need to perform the important work. Um, I think we need to have a better discussion a lot, I think a more productive discussion around. Um how to coordinate between the city and the utilities and and our right of way with local stakeholders like aldermanic offices. Um, but without layering in weeks and weeks of delays. And also, um, I think Alderman Lopez Ray Lopez brought up a very good point. About the cost of restorations. Why is it that the city? The The city's, uh, restoration costs are nearly double that of people's. Um, that doesn't square up and I have the same kind of frustrations. Ray Lopez, does we do a lot of utility work in the central business district? Right? That's where Commerce is. It's where 170,000 people live. Um, and so again I know that that's not going to slow down anytime soon. Um, but um we need better answers to these questions. I want to thank the citizens Utility Board for being here. Um and serving as our rate payer Advocate at the ICC. Um thank you for your testimony. I Rely Upon um Your advice on a regular basis and and then please also chair. I think, um, we need to talk as colleagues about what we can do. To try and assist in the effort to preserve Li Heap. Um, I really truly believe if we if we lose that program, that that could have a devastating impact on many, many tens of thousands of families in Chicago. So thank you madam chair. I appreciate the Indulgence. And uh almond Riley. June 13th is the uh summer preparedness hearing with comment. Yeah. Um, thank you for that. All right. Um, I think we don't have any other Alders on stack that are currently in the room, we did start another committee meeting um, in the other space. Um, I I just want want to reflect back. Um, a few things that I know we're going to take back through the committee. Um, so we'll make sure to follow up with any questions that were made through the chair and get those answers to all of our committee members, um, you know, to, um, Uh, our panelists today. Thank you each and every 1 of you, for always making the time for being here for um having responses to our questions. Thanks to our city departments, um, C dot, you know, we'll follow up. Um, so we can maybe dig into a little bit of the permitting process. Since that seems to be a thing, multiple members have questions about and president booner will look forward to hearing from your team. Um, a bit, as you guys get closer to kind of nailing down a time frame to see at what point um, you're ready to have that conversation again, with the city. If there are any kind of requests or proposals, um, around what the city could do around permitting. Um, and as we look at, uh, identifying those um, miles of pipeline, that need to be, um, uh, retired, Um, so I want to thank our guests today. Um, with there being no further business before the committee, uh, I'll take a motion to adjourn from. Alder Cruise. Thank you. Uh, last woman standing older person crew so moves. Um, it is 12:31 and uh hearing no objection, so ordered Meeting on the committee Environmental Protection energy is now adjourned.